In voyage chartering, the owner allows a specific amount of time (Laytime) for the charterer to load and discharge cargo. If this time is exceeded, the charterer pays Demurrage. If completed early, the owner pays Despatch.

The Core Question: When does the clock start?

Laytime commences based on the Notice of Readiness (NOR). The vessel must be an 'arrived ship', fully ready in all respects to load or discharge cargo.

Common Laytime Definitions

Term Meaning
SHINCSundays and Holidays Included. The clock runs continuously.
SHEXSundays and Holidays Excluded. The clock stops during these periods.
WWDWeather Working Days. Time stops if bad weather prevents loading.

Market Fact

In 2022, demurrage claims accounted for nearly 40% of all post-fixture disputes handled by major P&I clubs. Source: UK P&I Club Claims Review, 2023

Worked Example: Demurrage Calculation

Allowed laytime: 5 days. Actual time used: 7 days, 12 hours (7.5 days). Demurrage rate: $15,000/day.

Common Mistakes